Flyover at Pattom

The flyover with a proposed length of 1008m will begin from near the PSC office Pattom and end at the one way at Plamoodu.


Progress Made

An expert committee has given approval for land acquisition for flyover, which is a technical requirement for Light Metro.
Final design of the flyover has been submitted for the approval of Light Metro officials.


Next Milestones

The land acquisition procedures ahead of the construction of the flyover at Pattom will begin in August 2022  and the construction works are slated to begin in November 2022.

Implementing Agency

Trivandrum Development Authority (TRIDA) / Kerala Rapid Transit Corporation Ltd