Ring Roads under Capital City Development

This will form part of the second phase of the City Road Improvement Scheme. The State Cabinet had given Administrative Sanction (AS) for CRDP Capital Roads Improvement Programme Phase 2. Trivandrum Chamber of Commerce and Industry (TCCI) Administrative Sanction (AS) for widening Kesavadasapuram -Kazhakkoottam road, and acquisition of 6.7543 hectares of land, was issued in January 2017 (Ref GO (Rt) No.79/2017/PWD dated 16.01.2017). This is considered part of enabling works for Light Metro. However, the widening of the Kesavadasapuram – Kazhakkoottam road to four lanes is currently not part of the project.


Progress Made

Administrative Sanction (AS) accorded Rs 864 crore Budget allocation


Next Milestones

Complete land acquisition

Tender and select agency by March 2023

Complete project by 2026

Implementing Agency

Capital Region Development Project (CRDP-II)

Department

Public Works Department (PWD)

Member of Parliament

Shashi Tharoor

Minister

P A Mohamed Riyas

MLA

Kadakampally Surendran

V. Sivankutty

V. K. Prasanth

Adv. Antony Raju

Constituency

Thiruvananthapuram

Vattiyoorkavu

Nemom

Kazhakkoottam

Would you like to support this project